Naga Corp began pile cap excavation in the IER Primorye

       On the site of the integrated resort «Primorye» resident Naga Corp. began work on the excavation of soil for the pile cap. The work will take about three months; in parallel the investor will begin erecting a skeleton for the hotel building.

Naga еженедельный отчет foto

      The total area of ​​the first phase of the future complex will be almost 55 thousand square meters,  where the hotel, casino and multipurpose conference hall will be created. As the Primorsky Krai Development Corporation reported, works on the construction of the hotel complex Naga Vladivostok are conducted simultaneously in three directions.

      «The construction contractor has already installed half of the entire scope of the pile field. Every day more than six units of engineering equipment are involved, as well as two tower cranes, 35 workers areinvolved. In total almost 500 builders will be employed for the construction period at a time», representatives of the PKDC said.

        According to the company-developer of the gambling zone, in parallel with the construction of the pile foundation, ground works are being carried out for the construction of a pile cap, on which the skeleton of the hotel and entertainment complex will be installed.

PHOA9587

       «The functional purpose of the cap is to uniformly distribute the load to individual piles in a single structure. In parallel with the construction of a ground base, it is planned to erect a skeleton. The active phase of wireframe works is to begin this summer», said the investor's construction.

       Due to the plan for the implementation of the first phase, the hotel complex 4 * will be an eleven-storey building with 279 rooms of different classes, as well as a casino and a multipurpose concert hall. In total, almost 500 people will be involved in the construction of the new complex at a time.

     According to the company's management, the foreign resident of the gambling zone Primorye plans to complete construction works in 2019. The implementation of the second phase of the entertainment complex is designed until 2022.

       It is worth noting that the Asian investor Naga Corp. has a serious intention to develop the non-game sector on the territory of its facilities in the entertainment zone «Primorye» - the world trends in the development of gambling business recommend a model for the development of an integrated resort where the gaming zone will occupy only part of the entire range of services.

      At the moment the work is underway to create a hotel complex with the casino «Selena» from a group of Russian companies, "Diamond Fortune Holdings Prim» LLC. They plan to open their complexes in 2019. It is also planned that the plan for the construction of the second stage of Tigre de Cristal will be presented in July-August 2018.